I know that it needs to penetrate 1 1 2 into the stud.
Install cedar shingle siding nails.
Extend this row of shingles around the house using the level to keep the bottom edge horizontal.
Add the ridge cap across the peak of the roofline.
They ll rust thru before the shingle fails mike smith rhode island.
Attach the shake with a pair of 5d galvanized box nails and a shingle hatchet or hammer.
Installing cedar shakes is pretty much the same as installing shingles.
Length as per above if you are using a gun switch to the same size in ss as gun nails do not have a good enough galvanize to stand the conditions.
Apply both nails 3 4 inches from the edge of each shake or shingle and about 1 1 2 inches above the exposure line.
Hello i will be installing 3 4 cedar siding this weekend either t g or bevel.
Design build repair restore.
Use 2 nails per shingle at about 3 4 1 9 cm from each edge and 1 2 5 cm above the butt line of the overlapping shingle.
Use two fasteners to apply each certi label shingle or shake.
As you can see installing cedar shingles isn t a difficult process.
This is when each piece of cedar siding covers half of the one below it much like staggering and layering on cedar siding on top of one another to provide a scale like appearance.
Nails should be long enough to penetrate underlying materials in the cedar shingles at least 3 4 inches or all the way through.
If shingles are wider than 8 20 4 cm use 2 additional fasteners driven 1 2 5 cm apart near the center of the shingles.
My local hardware store does not sell 3 1 2 ring shanked so will i be ok.
For face nail under windows and the top course we use a small head ss.
Install shingles using 2 weather resistant nails.
Add remaining courses until you reach the roofline.
A few questions i have 1 whats the reccomended nail.
Whether you install clapboard t1 11 cedar shakes or board and batten siding on your house you can attach it with either nails or screws.
Step 5 attach the shingles with 1 inch roofing nails.
Use hand nails a carefully set up and adjusted siding gun or if it must be staples use wide crown across the gap of two so one leg is in each shingle.
This will be my first time so i would love a few pointers to get me on the right path.
Use a chalk line to align the starter course of cedar shingles.
Many builders choose nails because they re easier to.
The traditional way to install cedar shakes is through a method called single coursing.
Nail one of the shingles to the sheathing so it extends to the line then use a level to install the rest of the shingles in that row with their ends flush with each other.
The nails install 6 inches down from the upper thin edge of the shake and each is 1 inch from the outer.
For staples use 7 16 1 1 cm minimum crown.